Saturday, January 1, 2011

Lean Project Delivery - Integrated Project Delivery Case Studies

                               

 
 Lean to be Green


IPD Case Study
University of Winnipeg - Richardson College for the Environment

When high expectations for its new environmental facility hit up against the familiar obstacle of budget constraints, the University of Winnipeg found an unorthodox solution. Using a process called Integrated Project Delivery (IPD), it formed a partnership that integrated project participants in a cooperative team focused on a common goal, which was to deliver the best quality Richardson College for the Environment facility in the most cost-effective way.









 The adoption of the IPD process enabled our team to bring all of the team members to the table to solve the challenge of high expectations and low budget.  By implementing the IPD process we were able to fix a project that was significantly over budget and deliver a project that has the potential to become

“North Americas Most Energy Efficient Sustainable Laboratory Building.”


The selection of building systems to achieve paradigm shift changes in performance was achieved by designing innovative laboratory ventilation volume control and heat recovery systems.   RCFE will utilize a three level lab air change rate (Red-Yellow-Green Light System) that is based upon using the appropriate amount of air in the lab based upon the actual use. 




In addition to significantly reducing the amount of air that will be required to safely operate the labs, the project team has incorporated an industry leading SEMCO heat recovery wheel that has been developed in collaboration with John Hopkins Research Labs and Hospitals.  This heat recovery wheel will enable 80% heat recovering including fume hood exhaust.

The IPD process was key to meeting the schedule for this type of project as it would not have been possible to get executive approval for starting the building foundations without having confidence in the numbers for the significant major building envelope components, controls, mechanical and electrical systems. It was amazing how accurate the estimates were considering that they were based upon very preliminary design drawings.  This was achieved because the designers and contractors collaborated and had a meeting of the minds on best value building system solutions in real time.


 Sherman Kreiner, Director of Community Renewal Corp, needed the team to commit to a “True Fixed Price” that represented the final real number based upon a design that the contractors helped create and would be motivated to deliver.  That is where the value lies!    With a high level of contractor involvement in the design, we will deliver this project at lower cost and much lower risk as measured by a less than 2% contingency.


By using the IPD methodology, our team was able to significantly reduce project costs, meet the Owners project requirements of delivering a LEED Gold Signature Building, while having a process that needed to withstand the scrutiny of a financial and process audit. 

The University of Winnipeg recognizes the added value of the IPD method and, based upon the success of the RCFE and Buhler Center projects, are in the process of changing their procurement policy to make IPD their preferred project delivery method. 


Lean project delivery has enabled the IDI Project Management Group to deliver exceptional value for the U of W because the owner was willing to take a leadership role in adopting a new approach. This was possible by selecting and working with the best team available to optimize value.  It is as simple as that and open book keeps all the cards on the table so that even the financial auditor has been seen the evidence and has endorsed the process.

Murray Guy
Integrated Designs
Twitter Lean_tobe_Green

Additional Integrated Project Delivery Project Summaries


The Churchill Northern Studies Center
demonstrates that Integrated Project Delivery can help to minimize risk  on complicated northern sustainable projects.



IPD  our team to start construction prior to the design being complete so that we could meet infrastructure spending requirements. The establishment of a collaborative trustful relationship with contractors has been key in delivering this project to meet budget.




The Buhler Center
demonstrates that Integrated Project Delivery can be used to deliver a unique cost effective high performance Art Gallery for $212 per sq.ft.


By using the IPD methodology, our team was able to significantly reduce project costs and deliver a LEED Silver Art Gallery Building. 

The U of W recognizes the added value of the IPD method and is in the process of changing their procurement policy to make IPD their preferred process. 
                                                                                          
                                             

The Evident Office Building demonstrates that IPD is an effective process for having a high level of collaboration and value creation.



 Gold ++ Corporate Office Building 

 “The collaboration element of Integrated Project Delivery was fantastic, thedesign team and the contractors acted as though it was their money they were spending.”   
                                      CEO Dennis Birtles



The Nortep Large Family Sustainable Housing Project
demonstrates that IPD can deliver high  building for less capital cost with the right team.


This 8 unit project was constructed to minimize building loads utilizing double wall construction, triple glazed windows, heat recovery and was delivered for an amazing $170/sq.ft.   Waskahikan Builders delivered an exceptional project with a true spirit of collaboration.

Lean Project Delivery - Integrated Project Delivery for Net 0 Building Projects

 A new lean project delivery system Integrated Project Delivery (IPD) is based upon a relational contracting methodology. The IPD system enables the hiring the best team based upon qualifications and the ability to work together in a spirit of trust and collaboration to deliver the best value.   For the same budget this approach will enable our industry to build better building and do our part to offset the 40% of greenhouse emissions that come from buildings.  By eliminating 10% waste in the process it will be possible to build “Net 0 buildings for Net 0 additional capital cost.”





For more information please see Integrated Project Delivery Case Studies
or contact 
Murray Guy
Integrated Designs
Twitter Lean_tobe_Green

New Thinking for a Sustainable Building Industry


                       
    
 Lean to be Green




New Thinking is going to required if we are going to be able to eliminate the 35% of GHG from the building industry that is causing Climate Change and threatening our way of life and many species.








Based upon a book called Broken Buildings Busted Budgets there is a minimum of 10% waste in the way we design and build projects. 





Would that new NEW THINKING be that we can eliminate enough waste in the design and construction of buildings to achieve Net 0 energy use, with Net 0 change in project cost (Net 0-0)?








This type of thinking is required if we are ever going to achieve a sustainable building industry and fix an industry that contributes 40% of all greenhouse gas emissions. 
For more information about the the Integrated Project Delivery Process: 
Lean Project Delivery - Integrated Project Delivery Process 
Murray Guy
Integrated Designs
Twitter Lean_tobe_Green